Datacenter buildout tracker: capacity by operator, from SEC filings

Every site public operators disclosed to the SEC, by stage: 534 sites, 22 operators, 36,472 MW disclosed, 14,577 MW energized.

AS OF 10 AUGUST 2026 · SOURCE: GAMBIT · SOURCE DOCUMENTS: SEC 10-K / 10-Q / 8-K · CURRENT VALUES IN THE TERMINAL ↗

The pipeline, in six numbers

Built from the operators' own SEC filings, every row linked to its source. The map and per-site rows live in AI compute, Data centres.

How the tracker is sourced

The AI buildout is discussed in press releases and measured in nobody's spreadsheet. Gambit builds it from the one source that carries legal consequences for being wrong: the operators' own SEC filings. Each 10-K, 10-Q and 8-K is parsed for site-level disclosures (location, stage, megawatts, land), and every extracted row keeps a link back to the filing. 3,364 candidate disclosures were evaluated to produce the 869 site-filing rows behind this page.

This is the free summary layer. The live version (the map, the per-site rows, the filing links, the capacity-versus-committed history) is in the terminal.

Megawatts by pipeline stage

Announced → land → power → construction → operational. Each step is a new disclosure, so rows count filings, not sites.

Disclosed megawatts by pipeline stage, and the number of site-filing rows behind each. Source: Gambit, from SEC filings, as of 10 August 2026.
StageMW disclosedSite-filing rows
Announced 25,774 153
Land secured 3,863 126
Power secured 15,752 120
Under construction 12,930 103
Operational 14,576 367
All stages72,895869

Filings are not sites. 367 operational rows, far fewer campuses. Distinct sites: 534. Operator totals use the deduplicated basis.

Who has disclosed what

All 22 operators by disclosed MW. % operational is the share already live: owned power versus a press release.

Operators ranked by total disclosed megawatts, with distinct sites and the share of capacity already operational. Source: Gambit, from SEC filings, as of 10 August 2026.
OperatorMW disclosedSites% operational
Riot Platforms 5,640 20 57%
MARA Holdings 4,804 31 43%
IREN 4,720 17 36%
Greenidge Generation 3,474 17 10%
TeraWulf 2,717 19 32%
Applied Digital 2,523 34 54%
Hut 8 2,295 25 61%
Nebius 1,925 6 11%
CleanSpark 1,558 61 29%
Core Scientific 1,462 17 36%
Cipher Mining 1,167 18 83%
Galaxy Digital 1,060 3 75%
Soluna Holdings 1,033 29 33%
Digital Realty 807 42 2%
Iron Mountain 488 27 0%
Hive Digital 414 7 23%
Bit Digital 272 41 39%
BitFuFu 51 8 100%
Argo Blockchain 35 7 100%
Equinix 28 95 0%
Bitdeer none disclosed 8 n/a
CoreWeave none disclosed 2 n/a

All 22 operators, with each stage mix, are ranked in AI compute.

Rank every operator in the terminal ↗

None disclosed is not zero. Bitdeer and CoreWeave file sites without a megawatt figure.

More on reading the ranking

Bitdeer and CoreWeave appear in the filings with sites but no megawatt figure attached to them, so their capacity is shown as none disclosed rather than as zero capacity.

Equinix and Iron Mountain disclose many sites at early stages and little energized capacity in this dataset, which is a fact about what they file, not about what they operate.

The twelve largest, with their filings

Largest single-site disclosures, each one click from its SEC EDGAR filing.

The twelve largest single-site capacity disclosures, each linked to the SEC filing it was extracted from. Source: Gambit, as of 10 August 2026.
OperatorSiteStageMWFiling
Greenidge Generation Texas Development Sites Announced 2,000 EDGAR ↗
Digital Realty Astra Enterprise Park Announced 2,000 EDGAR ↗
MARA Holdings Matagorda County, Texas Power secured 2,000 EDGAR ↗
IREN West Texas Announced 1,400 EDGAR ↗
TeraWulf Muskie Data Campus Under construction 1,000 EDGAR ↗
Core Scientific Pecos, TX Announced 1,000 EDGAR ↗
Riot Platforms Corsicana, TX Under construction 1,000 EDGAR ↗
Riot Platforms Corsicana, TX Announced 1,000 EDGAR ↗
Riot Platforms Facility Land Under construction 1,000 EDGAR ↗
Greenidge Generation Texas Generation Sites Announced 1,000 EDGAR ↗
Digital Realty Northern Virginia Announced 1,000 EDGAR ↗
Riot Platforms Navarro County, TX Announced 1,000 EDGAR ↗

Every disclosed site, mapped and linked to its filing, is in AI compute.

Open the buildout map ↗

Power, and the queue in front of it

Disclosed capacity is an intention; energized capacity is a fact. The gap is a grid connection: the queue is roughly 29x this whole pipeline.

The numbers behind the queue

4,029 projects representing 1,068,260 MW are waiting in interconnection queues, roughly 29 times the entire disclosed datacenter pipeline in this tracker, with MISO the largest single utility. Against that, 14,577 MW of the 36,472 MW disclosed is live today, and the latest announced-to-operational lag is 8.7 months across 86 matched pairs.

How the tracker is built

Method in full

Each row is a named place, a stage, a megawatt figure, a date and a filing URL. Nothing comes from an analyst estimate or a trade-press megawatt guess.

Operator totals use the product's deduplicated basis. Summing filing rows per operator double-counts multi-filing sites and overstates capacity, an easy and common error with this kind of data.

It is not a census of world datacenter capacity. Private operators and the hyperscalers' unfiled capacity are outside it by construction: if it was never disclosed in a filing, it is not here.

Questions

How much datacenter capacity has been disclosed in total?

36,472 MW across 534 distinct sites and 22 operators, of which 14,577 MW is energized. Every megawatt in that figure was extracted from a company's own SEC filing.

How many datacenter sites are actually operational?

14,576 MW sits at the operational stage, from 367 filing rows, not 367 sites: one site is re-disclosed as it advances. The dataset holds 534 distinct sites.

Which operator has the most disclosed megawatts?

Riot Platforms, at 5,640 MW across 20 sites, 57% of it operational. MARA Holdings follows at 4,804 MW and IREN at 4,720 MW.

Where does the data come from?

SEC 10-K, 10-Q and 8-K filings, parsed per site and stage. 853 of 869 site-filing rows link to SEC EDGAR; the other 16 to the operator's own primary disclosure. Every row keeps its link.

How long does it take a datacenter to go from announcement to operation?

8.7 months at the latest reading, across 86 matched announcement and energization pairs. Power binds upstream: 4,029 projects, 1,068,260 MW, sit in the interconnection queue, MISO the largest utility.

What this page leaves out

Twelve sites and the ranking here. The desk maps every site, with its filing and stage.