Datacenter buildout tracker: capacity by operator, from SEC filings

Every datacenter site a public operator has disclosed to the SEC, parsed per site and per stage: 534 sites, 22 operators, 36,472 MW announced through operational, and 14,577 MW already energized.

AS OF 10 AUGUST 2026 · SOURCE: GAMBIT · SOURCE DOCUMENTS: SEC 10-K / 10-Q / 8-K · CURRENT VALUES IN THE TERMINAL ↗

The pipeline, in six numbers

The AI buildout is discussed in press releases and measured in nobody's spreadsheet. Gambit builds it from the one source that carries legal consequences for being wrong: the operators' own SEC filings. Each 10-K, 10-Q and 8-K is parsed for site-level disclosures (location, stage, megawatts, land), and every extracted row keeps a link back to the filing. 3,364 candidate disclosures were evaluated to produce the 869 site-filing rows behind this page.

This is the free summary layer. The live version (the map, the per-site rows, the filing links, the capacity-versus-committed history) is on the DATA desk in the terminal.

The five stages

Megawatts by pipeline stage

A site moves announced → land secured → power secured → under construction → operational, and it is disclosed again at each step. The megawatt column is what has been disclosed at that stage; the row count is filings, not sites.

Disclosed megawatts by pipeline stage, and the number of site-filing rows behind each. Source: Gambit, from SEC filings, as of 10 August 2026.
StageMW disclosedSite-filing rows
Announced 25,774 153
Land secured 3,863 126
Power secured 15,752 120
Under construction 12,930 103
Operational 14,576 367
All stages72,895869

Filings are not sites. 367 rows sit at the operational stage, but they describe far fewer physical places: one campus reappears in every quarterly filing that mentions it. The distinct site count for the whole dataset is 534, and totals by operator below use the product's own deduplicated basis rather than a sum of filing rows.

Capacity by operator

Who has disclosed what

All 22 operators in the dataset, ranked by total disclosed megawatts. % operational is the share of that operator's disclosed capacity currently at the operational stage. It is the difference between a company that owns power and one that owns a press release.

Operators ranked by total disclosed megawatts, with distinct sites and the share of capacity already operational. Source: Gambit, from SEC filings, as of 10 August 2026.
OperatorMW disclosedSites% operational
Riot Platforms 5,640 20 57%
MARA Holdings 4,804 31 43%
IREN 4,720 17 36%
Greenidge Generation 3,474 17 10%
TeraWulf 2,717 19 32%
Applied Digital 2,523 34 54%
Hut 8 2,295 25 61%
Nebius 1,925 6 11%
CleanSpark 1,558 61 29%
Core Scientific 1,462 17 36%
Cipher Mining 1,167 18 83%
Galaxy Digital 1,060 3 75%
Soluna Holdings 1,033 29 33%
Digital Realty 807 42 2%
Iron Mountain 488 27 0%
Hive Digital 414 7 23%
Bit Digital 272 41 39%
BitFuFu 51 8 100%
Argo Blockchain 35 7 100%
Equinix 28 95 0%
Bitdeer none disclosed 8 n/a
CoreWeave none disclosed 2 n/a

All 22 operators, with the stage mix behind each one, are ranked on the DATA desk.

Rank every operator in the terminal ↗

Zero is a real reading. Bitdeer and CoreWeave appear in the filings with sites but no megawatt figure attached to them, so their capacity is shown as none disclosed rather than as zero capacity. Equinix and Iron Mountain disclose many sites at early stages and little energized capacity in this dataset, which is a fact about what they file, not about what they operate.

Traceability

Twelve of the largest disclosures, with their filings

Every row in the tracker carries the document it came from. Here are the twelve largest single-site capacity disclosures, each linked to the filing on SEC EDGAR, so the chain from this table to the original sentence is one click long.

The twelve largest single-site capacity disclosures, each linked to the SEC filing it was extracted from. Source: Gambit, as of 10 August 2026.
OperatorSiteStageMWFiling
Greenidge Generation Texas Development Sites Announced 2,000 EDGAR ↗
Digital Realty Astra Enterprise Park Announced 2,000 EDGAR ↗
MARA Holdings Matagorda County, Texas Power secured 2,000 EDGAR ↗
IREN West Texas Announced 1,400 EDGAR ↗
TeraWulf Muskie Data Campus Under construction 1,000 EDGAR ↗
Core Scientific Pecos, TX Announced 1,000 EDGAR ↗
Riot Platforms Corsicana, TX Under construction 1,000 EDGAR ↗
Riot Platforms Corsicana, TX Announced 1,000 EDGAR ↗
Riot Platforms Facility Land Under construction 1,000 EDGAR ↗
Greenidge Generation Texas Generation Sites Announced 1,000 EDGAR ↗
Digital Realty Northern Virginia Announced 1,000 EDGAR ↗
Riot Platforms Navarro County, TX Announced 1,000 EDGAR ↗

Every disclosed site, mapped and linked to the filing that named it, is on the DATA desk.

Open the buildout map ↗

The constraint

Power, and the queue in front of it

Disclosed capacity is an intention; energized capacity is a fact. The gap between the two is a grid connection. 4,029 projects representing 1,068,260 MW are waiting in interconnection queues, roughly 29 times the entire disclosed datacenter pipeline in this tracker, with MISO the largest single utility. Against that, 14,577 MW of the 36,472 MW disclosed is live today, and the latest announced-to-operational lag is 8.7 months across 86 matched pairs.

Method

How the tracker is built

Filings only, per site and per stage. The source is SEC 10-K, 10-Q and 8-K documents: 853 of 869 site-filing rows link to a document on EDGAR, the other 16 to the operator's own primary disclosure where the filing points there. Each row is a named place, a stage, a megawatt figure, a date and a filing URL. Nothing comes from an analyst estimate or a trade-press megawatt guess.

Deduplication. Operator totals use the product's deduplicated basis. Summing filing rows per operator double-counts multi-filing sites and overstates capacity, an easy and common error to make with this kind of data.

What it is not. It is not a census of world datacenter capacity. Private operators and the hyperscalers' unfiled capacity are outside it by construction: if it was never disclosed in a filing, it is not here.

Questions

How much datacenter capacity has been disclosed in total?

36,472 MW across 534 distinct sites and 22 operators, of which 14,577 MW is energized. Every megawatt in that figure was extracted from a company's own SEC filing.

How many datacenter sites are actually operational?

14,576 MW sits at the operational stage. That number comes from 367 operational-stage site-filing rows, not 367 sites. A single site is disclosed repeatedly as it moves through the pipeline, so filing rows always outnumber sites. The distinct site count across the whole dataset is 534.

Which operator has the most disclosed megawatts?

Riot Platforms, at 5,640 MW across 20 sites, 57% of it operational. MARA Holdings follows at 4,804 MW and IREN at 4,720 MW.

Where does the data come from?

Company filings with the U.S. Securities and Exchange Commission (10-K, 10-Q and 8-K), parsed per site and per stage. 853 of the 869 site-filing rows link to a document on SEC EDGAR; the remaining 16 link to the operator's own primary disclosure where that is the source. In the terminal every row carries its link, so any number here can be traced back to the sentence it came from.

How long does it take a datacenter to go from announcement to operation?

The latest announced-to-operational lag in this dataset is 8.7 months, measured across 86 matched pairs of announcement and energization disclosures. The binding constraint upstream is power: the interconnection queue holds 4,029 projects totalling 1,068,260 MW, with MISO the largest single utility.

The live desk

What this page leaves out

This page publishes twelve of the largest disclosures and the operator ranking. The desk holds every site the tracker knows about, placed on a map, each one carrying the filing that disclosed it and the stage it has reached.